Water, Sanitation, and Hygiene (WASH) · Completed

WASH Initiative in Hai Gabat

A targeted initiative to improve access to clean water and promote hygiene awareness in Hai Gabat, Juba, through direct community involvement and resource distribution.

Where
Hai Gabat, Juba
When
September to December 2022
Reached
38 households (~200 individuals)

DASA flood assessment · Hai Gabat, Juba, October 2022

Results

What changed

Improved hygiene practices in 38 households (~200 individuals), with a reported increase from 30% to 75% in hygiene awareness and adoption.

Achievements

  • Increased hygiene awareness from 30% to 75% post-activity.
  • High community engagement led to self-organized maintenance committees for the water tank.
  • Successful distribution of hygiene kits to 38 households.

What was counted

  • % of respondents who report improved hygiene practices (Baseline: 30%, Post-activity: 75%).

The work

What the project did

Objectives

  • Improve access to clean water for residents of Hai Gabat.
  • Increase hygiene awareness and adoption of best practices.
  • Empower local communities to sustain water and sanitation efforts.

Activities

  • Conducted needs assessment.
  • Engaged stakeholders, including Block Council, Juba City Council, and community representatives.
  • Trained volunteers on hygiene promotion messaging.
  • Distributed 20L buckets with lids, AquaTabs, and washing soap to affected households.
  • Conducted feedback interviews and impact assessment after 1-2 months.

Learning

Challenges and lessons

Challenges

  • Low awareness of hygiene best practices. Solution: Used local leaders and a door-to-door campaign to increase participation.

Lessons learned

  • Future initiatives should include maintenance training to sustain infrastructure.

Keeping it going

  • Community-led water tank maintenance team established.
  • Local vendors identified for future supply of hygiene items.

Reports

  • Final project report available.
  • Financial reports submitted, no compliance issues noted.